Parsn Construction And Developers Private Limited

Type CompanyRERA projects 5Districts Mumbai Suburban
BUILDER THOK
Ruko
5 of 5projects with possession moved
48 moaverage extension when late
2lapsed registrations
5MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Jun 2018Jun 2025
84 mo
Jun 2021Dec 2025
54 mo
Dec 2022Dec 2025
36 mo
Dec 2024Apr 2029
52 mo

Signals from filings & records

2 projects lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Kurla Sahayog CHS Ltd., Bldg. No.68
P51800009819 · Kurla
Ruko
Nehru Nagar Panchratna CHS Ltd, Bldg. No.5
P51800015096 · Kurla
Ruko
Nehru Nagar Sharada CHS LTD Bldg NO. 62
P51800014914 · Kurla
Ruko
Vighnaharta SRA CHS LTD
P51800016404 · Kurla
Ruko
Nehru Nagar Shiv Vaibhav CHS LTD Bldg No 38
P51800032409 · Kurla
Dhyaan Do