BUILDER

Parte Developers

Type Firm / individualRERA projects 1Districts Pune
BUILDER THOK
Ruko
0 of 1projects with possession moved
0 moaverage extension when late
1lapsed registrations
1MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Paramsundar
Dhayari (part) · lapsed
Dec 2017Dec 2017
on time

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Paramsundar
P52100010772 · Dhayari (part)
Ruko