Poddar Housing And Development Limited

Type CompanyRERA projects 4Districts Thane, Mumbai City
BUILDER THOK
Ruko
1 of 4projects with possession moved
9 moaverage extension when late
2lapsed registrations
4MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Mar 2018Mar 2018
not moved
Mar 2019Mar 2019
not moved
Poddar Spraha Diamond Phase-i
Mumbai City · lapsed
Dec 2021Sept 2022
9 mo
Poddar Wondercity Phase - I
Badlapur (M Cl) · lapsed
Sept 2023Sept 2023
lapsed

Signals from filings & records

2 projects lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Samruddhi Evergreens-phase-4a
P51700009407 · Badlapur (M Cl)
Ruko
Samruddhi Evergreen-phase-4b
P51700009016 · Badlapur (M Cl)
Ruko
Poddar Spraha Diamond Phase-i
P51900002986 · Mumbai City
Ruko
Poddar Wondercity Phase - I
P51700020032 · Badlapur (M Cl)
Ruko