BUILDER

Puneet Builders

Type Firm / individualRERA projects 3Districts Mumbai Suburban
BUILDER THOK
Ruko
0 of 3projects with possession moved
0 moaverage extension when late
3lapsed registrations
3MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Jun 2025Jun 2025
lapsed
Jun 2025Jun 2025
lapsed
Jun 2025Jun 2025
lapsed

Signals from filings & records

3 projects lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Puneet Prime Phase 1 Floor 0 To Floor 2
P51800020798 · Kurla
Ruko
Puneet Prime Phase 2 Floor 3 To Floor 16
P51800020753 · Kurla
Ruko
Puneet Prime Phase 3 Floor 17 To Floor 18
P51800020793 · Kurla
Ruko