BUILDER

Rahul Mandaleshwar Kale

Type Firm / individualRERA projects 1Districts Nashik
BUILDER THOK
Ruko
1 of 1projects with possession moved
4 moaverage extension when late
1lapsed registrations
1MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Tirupati Hills
Nashik · lapsed
Mar 2026Jul 2026
4 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements