BUILDER

Rajheramb Properties

Type Firm / individualRERA projects 6Districts Pune
BUILDER THOK
Ruko
4 of 4projects with possession moved
40 moaverage extension when late
0lapsed registrations
6MahaRERA projects · 2 being verified

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Jun 2018Jun 2019
12 mo
Dec 2018Jun 2022
42 mo
Jan 2024May 2028
52 mo
1 Hallmark Aveneu Phase II
Pimpri Chinchawad (M Corp.)
Apr 2024Aug 2028
52 mo
2 more projects are being verified or have no declared dates yet.

Signals from filings & records

Verification in progressMahaRERA

4 of 6 projects verified against the live MahaRERA record so far. Stats above use verified projects only.

Thok Bajaake crawler
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Venkatesh Imperia Phase I
P52100002796 · Punawale
Not scored
Venkatesh Imperia Phase II
P52100002301 · Punawale
Ruko
Venkatesh Aveneu
P52100024485 · Mulshi
Ruko
1 Hallmark Aveneu Phase II
P52100020694 · Pimpri Chinchawad (M Corp.)
Ruko
Regalia Residency
P52100001872 · Bavadhan Bk
Not scored
1 Hallmark Avenue Phase I
P52100002760 · Pimpri Chinchawad (M Corp.)
Not scored