BUILDER

Ramesh Sawant

Type Firm / individualRERA projects 1Districts Thane
BUILDER THOK
Ruko
1 of 1projects with possession moved
21 moaverage extension when late
1lapsed registrations
1MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Devashree Park
Thane (M Corp.) · lapsed
Mar 2022Dec 2023
21 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Devashree Park
P51700015920 · Thane (M Corp.)
Ruko