BUILDER

Ravima Developer

Type Firm / individualRERA projects 7Districts Pune
BUILDER THOK
Ruko
5 of 7projects with possession moved
11 moaverage extension when late
3lapsed registrations
7MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
The Work Club Phase I
Pimpri Chinchawad (M Corp.)
Apr 2023Apr 2023
not moved
The Work Club Phase II
Haveli · lapsed
Jun 2024Jun 2025
12 mo
Apr 2025Nov 2025
7 mo
Sept 2025Sept 2025
lapsed
Dec 2025Apr 2028
28 mo
Dec 2028Apr 2029
4 mo

Signals from filings & records

3 projects lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

The Work Club Phase I
P52100021171 · Pimpri Chinchawad (M Corp.)
Ruko
The Work Club Phase II
P52100027555 · Haveli
Ruko
Newton Homes Tathawade Phase I
P52100031983 · Mulshi
Ruko
Newton Homes Hadapsar Near Runwal Seagull Phase I
P52100048243 · Pune City
Ruko
The Work Club Hadapsar
P52100053032 · Haveli
Ruko
Newton Homes Hadapsar Near Runwal Seagull Phase II
P52100077513 · Haveli
Pakka
Newton Homes Tathawade Phase II
P52100052803 · Mulshi
Pakka