BUILDER

Reliable Tarang

Type Firm / individualRERA projects 3Districts Palghar
BUILDER THOK
Ruko
3 of 3projects with possession moved
83 moaverage extension when late
1lapsed registrations
3MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Aug 2018Dec 2025
88 mo
Aug 2018Dec 2025
88 mo
Reliable Swapna Nagri-9,10,11,12
Vasai-virar City (M Corp) · lapsed
Dec 2019Dec 2025
72 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Reliable Swapna Nagari-1,2,5,8,13,14,15
P99000007894 · Vasai-virar City (M Corp)
Ruko
Reliable Swapna Nagari-21,22,23,24,25,26,27
P99000012328 · Vasai-virar City (M Corp)
Ruko
Reliable Swapna Nagri-9,10,11,12
P99000008641 · Vasai-virar City (M Corp)
Ruko