BUILDER

Rishikesh Builders & Developers

Type Firm / individualRERA projects 3Districts Nashik
BUILDER THOK
Ruko
2 of 3projects with possession moved
55 moaverage extension when late
0lapsed registrations
3MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Sept 2022Dec 2027
63 mo
Mar 2023Mar 2023
not moved
Jun 2024Apr 2028
46 mo

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Tulasi Baug
P51600026532 · Nashik
Ruko
Nandlal Plaza
P51600023461 · Nashik
Ruko
Tulasi Baug
P51600027664 · Nashik
Ruko