BUILDER

Rohit Infra

Type Firm / individualRERA projects 3Districts Pune
BUILDER THOK
Ruko
1 of 1projects with possession moved
18 moaverage extension when late
1lapsed registrations
3MahaRERA projects · 2 being verified

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Rohit Pinnacle
Pimpri Chinchawad (M Corp.) · lapsed
Aug 2019Feb 2021
18 mo
2 more projects are being verified or have no declared dates yet.

Signals from filings & records

Verification in progressMahaRERA

1 of 3 projects verified against the live MahaRERA record so far. Stats above use verified projects only.

Thok Bajaake crawler
1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Rohit Pinnacle
P52100004032 · Pimpri Chinchawad (M Corp.)
Ruko
Rohit Palms
P52100002481 · Pimpri Chinchawad (M Corp.)
Not scored
Platinum
P52100016424 · Mulshi
Not scored