BUILDER

Rudra Infra

Type Firm / individualRERA projects 4Districts Pune, Raigarh, Nashik
BUILDER THOK
Dhyaan Do
4 of 4projects with possession moved
14 moaverage extension when late
1lapsed registrations
4MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Ramkrishna Residency
Pimpri Chinchawad (M Corp.) · lapsed
Jan 2021Feb 2024
37 mo
Dec 2026Apr 2027
4 mo
Dec 2026Dec 2027
12 mo
Dec 2028Apr 2029
4 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Ramkrishna Residency
P52100012025 · Pimpri Chinchawad (M Corp.)
Ruko
Vijay Residency
P52100016655 · Haveli
Pakka
Bhaveshwar Rudra
P52000048978 · Panvel
Dhyaan Do
Sitai Heights 2
P51600078196 · Nashik
Pakka