1 of 2projects with possession moved
4 moaverage extension when late
0lapsed registrations
4MahaRERA projects · 2 being verified

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Jul 2025Jul 2025
not moved
Dec 2030Apr 2031
4 mo
2 more projects are being verified or have no declared dates yet.

Signals from filings & records

Verification in progressMahaRERA

2 of 4 projects verified against the live MahaRERA record so far. Stats above use verified projects only.

Thok Bajaake crawler
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Rutuviraj Apartment
P51500028674 · Aurangabad
Ruko
Rutuja Residency
P51500077524 · Aurangabad
Pakka
Yashraj Tower
P51500005659 · Aurangabad (M Corp.)
Not scored
Yashraj Angan
P51500014780 · Aurangabad (M Corp.)
Not scored