BUILDER

Saifortune Builders And Developers Private Limited

Type CompanyRERA projects 1Districts Raigarh
BUILDER THOK
Ruko
1 of 1projects with possession moved
48 moaverage extension when late
1lapsed registrations
1MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Kolad Hills
Kolad · lapsed
Dec 2021Dec 2025
48 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements