BUILDER

Saish Group

Type Firm / individualRERA projects 2Districts Thane
BUILDER THOK
Dhyaan Do
1 of 2projects with possession moved
4 moaverage extension when late
1lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Maitreya Imperial
Kalyan · lapsed
May 2025May 2025
lapsed
Aug 2028Dec 2028
4 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Maitreya Imperial
P51700078872 · Kalyan
Ruko
Maitreya Mandai Legacy
P51700078914 · Kalyan
Pakka