BUILDER

Salangpur Gruh Nirman

Type Firm / individualRERA projects 3Districts Thane
BUILDER THOK
Ruko
3 of 3projects with possession moved
9 moaverage extension when late
0lapsed registrations
3MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Salasar Aarpan A Wing
Mira-bhayandar (M Corp.)
Jun 2019Jun 2020
12 mo
Salasar Aarpan B Wing
Mira-bhayandar (M Corp.)
Dec 2019Dec 2020
12 mo
Dec 2027Apr 2028
4 mo

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Salasar Aarpan A Wing
P51700010292 · Mira-bhayandar (M Corp.)
Ruko
Salasar Aarpan B Wing
P51700010843 · Mira-bhayandar (M Corp.)
Ruko
Salasar Aavatar
P51700048170 · Thane
Pakka