BUILDER

Samruddhi Buildcon

Type Firm / individualRERA projects 4Districts Thane, Raigarh, Nashik
BUILDER THOK
Dhyaan Do
2 of 2projects with possession moved
21 moaverage extension when late
0lapsed registrations
4MahaRERA projects · 2 being verified

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Jul 2024Jan 2027
30 mo
Dec 2025Dec 2026
12 mo
2 more projects are being verified or have no declared dates yet.

Signals from filings & records

Verification in progressMahaRERA

2 of 4 projects verified against the live MahaRERA record so far. Stats above use verified projects only.

Thok Bajaake crawler
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Samruddhi Flora
P51700053740 · Bhiwandi
Ruko
Sai Samruddhi
P51700051140 · Thane
Dhyaan Do
Samruddhi Complex
P52000021641 · Panvel
Not scored
Siddhivinayak Annex
P51600029128 · Nashik
Not scored