BUILDER

Santosh Machindra Shinde

Type Firm / individualRERA projects 2Districts Ahmednagar
BUILDER THOK
Ruko
1 of 2projects with possession moved
4 moaverage extension when late
0lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Samruddhi Park Phase 2
Ahmadnagar (M Corp.)
Feb 2018Feb 2018
not moved
Mar 2030Jul 2030
4 mo

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Samruddhi Park Phase 2
P52200011133 · Ahmadnagar (M Corp.)
Ruko
Shaniraj Heights
P52200079785 · Nagar
Pakka