Sapphire Space Infracon PVT LTD

Type CompanyRERA projects 5Districts Palghar
BUILDER THOK
Ruko
0 of 5projects with possession moved
0 moaverage extension when late
5lapsed registrations
5MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Sathyanagar Phase 1
Newale · lapsed
Jan 2021Jan 2021
lapsed
Sathyanagar Phase 5
Newale · lapsed
Jan 2021Jan 2021
lapsed
Sathyanagar Phase 2
Newale · lapsed
Jan 2021Jan 2021
lapsed
Sathyanagar Phase 3
Newale · lapsed
Jan 2021Jan 2021
lapsed
Sathyanagar Phase 4
Newale · lapsed
Jan 2021Jan 2021
lapsed

Signals from filings & records

5 projects lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Sathyanagar Phase 1
P99000011436 · Newale
Ruko
Sathyanagar Phase 5
P99000010497 · Newale
Ruko
Sathyanagar Phase 2
P99000008795 · Newale
Ruko
Sathyanagar Phase 3
P99000009459 · Newale
Ruko
Sathyanagar Phase 4
P99000010507 · Newale
Ruko