Satish Baswant Patil

Type Firm / individualRERA projects 2Districts Pune
BUILDER THOK
Ruko
2 of 2projects with possession moved
25 moaverage extension when late
1lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Ganesh Royal
Pimpri Chinchawad (M Corp.) · lapsed
Dec 2017Dec 2018
12 mo
Siddhi Towers A Wing
Pimpri Chinchawad (M Corp.)
Dec 2019Jan 2023
37 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Ganesh Royal
P52100010138 · Pimpri Chinchawad (M Corp.)
Ruko
Siddhi Towers A Wing
P52100007014 · Pimpri Chinchawad (M Corp.)