Shree Neelkamal Housing & Infrastructure

Type Firm / individualRERA projects 4Districts Nashik
BUILDER THOK
Dhyaan Do
3 of 4projects with possession moved
20 moaverage extension when late
1lapsed registrations
4MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Dec 2025Apr 2030
52 mo
Neelkamal Sarita Phase 2
Dindori · lapsed
Dec 2025Dec 2025
lapsed
Dec 2026Apr 2027
4 mo
Dec 2026Apr 2027
4 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Neelkamal Sarita Phase 1
P51600046001 · Dindori
Ruko
Neelkamal Sarita Phase 2
P51600045682 · Dindori
Ruko
Neelkamal Sarita Phase 4
P51600049056 · Dindori
Pakka
Neelkamal Sarita Phase 3
P51600054554 · Dindori
Pakka