Type Firm / individualRERA projects 2Districts Thane, Nashik
BUILDER THOK
Ruko
2 of 2projects with possession moved
22 moaverage extension when late
1lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Swapna Rekha CHS
Ambarnath · lapsed
Dec 2025Oct 2026
10 mo
Sadguru Homes
Nashik (M Corp.)
Mar 2026Dec 2028
33 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Swapna Rekha CHS
P51700046892 · Ambarnath
Ruko
Sadguru Homes
P51600022296 · Nashik (M Corp.)
Ruko