BUILDER

Shree Samarth Enterprises

Type Firm / individualRERA projects 4Districts Thane
BUILDER THOK
Pakka
1 of 1projects with possession moved
4 moaverage extension when late
0lapsed registrations
4MahaRERA projects · 3 being verified

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Sept 2028Jan 2029
4 mo
——
—
Deepsamay CHS
Ambarnath
——
—
——
—

Signals from filings & records

Verification in progressMahaRERA

1 of 4 projects verified against the live MahaRERA record so far. Stats above use verified projects only.

Thok Bajaake crawler
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Swaraswati Heights
P51700055115 · Ambarnath
Pakka
Raj Vaibhav Park
PM1330002600949 · Kalyan
Not scored
Deepsamay CHS
P51700080595 · Ambarnath
Not scored
Om Dutta Deep Co. Op Hsg
P51700054486 · Ambarnath
Not scored