BUILDER

Shreepati Build Infra Investment Limited

Type CompanyRERA projects 3Districts Mumbai City
BUILDER THOK
Ruko
2 of 3projects with possession moved
62 moaverage extension when late
1lapsed registrations
3MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Dec 2019Apr 2027
88 mo
Shreepati Aradhana
Abcd-400002 · lapsed
Dec 2019Dec 2022
36 mo
Dec 2026Dec 2026
not moved

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Shreepati Coronet
P51900000623 · E-400010
Ruko
Shreepati Aradhana
P51900000558 · Abcd-400002
Ruko
Shreepati Bayview
P51900010019 · Abcd-400004
Ruko