BUILDER

Shriniwas Constructions

Type Firm / individualRERA projects 2Districts Sangli
BUILDER THOK
Ruko
0 of 2projects with possession moved
0 moaverage extension when late
1lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Sadanand Residency
Sangli Miraj Kupwad (M Corp.)
Feb 2021Feb 2021
not moved
Dinkar Residency
Sangli Miraj Kupwad (M Corp.) · lapsed
Apr 2023Apr 2023
lapsed

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Sadanand Residency
P53100016270 · Sangli Miraj Kupwad (M Corp.)
Ruko
Dinkar Residency
P53100028475 · Sangli Miraj Kupwad (M Corp.)
Ruko