BUILDER

Sneh Makewell LLP

Type LLPRERA projects 2Districts Thane
BUILDER THOK
Dhyaan Do
1 of 2projects with possession moved
18 moaverage extension when late
0lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Jun 2021Dec 2022
18 mo
Jul 2028Jul 2028
not moved

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Dynamic Crest Phase I - Rimo/everest
P51800001460 · Thane (M Corp.)
Ruko
Dynamic Crest Phase II - Titlis
P51700079627 · Thane
Pakka