BUILDER

Sunguard Builders LLP

Type LLPRERA projects 4Districts Pune
BUILDER THOK
Ruko
1 of 4projects with possession moved
4 moaverage extension when late
1lapsed registrations
4MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Dec 2018Dec 2018
not moved
Jun 2022Jun 2022
not moved
Park Ivory Phase III
Mulshi · lapsed
Apr 2024Apr 2024
lapsed
Dec 2029Apr 2030
4 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Park Ivory Phase III Commercial
P52100016811 · Mulshi
Ruko
Park Ivory Phase II
P52100015699 · Wakad
Ruko
Park Ivory Phase III
P52100030055 · Mulshi
Ruko
The Raya Phase I
PR1260002502741 · Mulshi
Pakka