BUILDER
Supertech Limited
BUILDER THOK
Ruko
18 of 27projects with possession moved
8 moaverage extension when late
0lapsed registrations
27UP RERA projects
Delivery track record
Possession date first declared vs latest on UP RERA
PROJECTPROMISEDLATESTMOVED BY
Emerald Court Phase II (Apex & Ceyane) - Demolished As Per The Order Of Hon'ble Superme Court
Jun 2021Nov 2021Gautam Buddha Nagar
5 mo
Showing 25 of 27 dated projects.
Signals from filings & records
No approved insolvency matchIBBI
No IBBI announcement has been matched to this builder after review.
IBBI public announcements
Projects
Supertech Eco Village-i Phase I-C
UPRERAPRJ8334 · Gautam Buddha Nagar
Supertech Eco Village-ii Phase I-C
UPRERAPRJ8337 · Gautam Buddha Nagar
Supertech Ecociti - Phase-1
UPRERAPRJ9744 · Gautam Buddha Nagar
Supertech Upcountry (Plotted)
UPRERAPRJ8267 · Gautam Buddha Nagar
Supertech Eco Village-i (Phase-i)
UPRERAPRJ4318 · Gautam Buddha Nagar
Eco Village-ii (Phase-i)
UPRERAPRJ4112 · Gautam Buddha Nagar
Supertech Czar
UPRERAPRJ9414 · Gautam Buddha Nagar
Supertech Eco Village-iii (Phase-i)
UPRERAPRJ604 · Roza Yakubpur
Supertech Eco Village-i (Phase-ii)
UPRERAPRJ4830 · Gautam Buddha Nagar
Supertech Upcountry Gh-02 Phase-01
UPRERAPRJ8263 · Gautam Buddha Nagar
Supertech Upcountry Gh-01 Phase-02
UPRERAPRJ8249 · Gautam Buddha Nagar
Supertech Eco Village-ii (Phase-ii)
UPRERAPRJ4917 · Gautam Buddha Nagar