BUILDER

Supreme Developers

Type Firm / individualRERA projects 3Districts Pune, Thane
BUILDER THOK
Ruko
3 of 3projects with possession moved
15 moaverage extension when late
0lapsed registrations
3MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Kingstone Avenue Ph 1
Pimpale Saudagar
Dec 2018Dec 2019
12 mo
Dec 2024Apr 2027
28 mo
Apr 2027Aug 2027
4 mo

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Kingstone Avenue Ph 1
P52100001909 · Pimpale Saudagar
Ruko
Kingston Avenue Phase II
P52100047815 · Haveli
Ruko
Crystal Heights
P51700055860 · Ambarnath
Pakka