Suraj Manglaprasad Mishra

Type Firm / individualRERA projects 1Districts Palghar
BUILDER THOK
Ruko
1 of 1projects with possession moved
32 moaverage extension when late
1lapsed registrations
1MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Jay Maa Residency Phase 2
Palghar · lapsed
Oct 2022Jun 2025
32 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Jay Maa Residency Phase 2
P99000029158 · Palghar
Ruko