BUILDER
Surbhi Midas Construction
BUILDER THOK
Ruko
1 of 1projects with possession moved
28 moaverage extension when late
0lapsed registrations
1MahaRERA projects
Delivery track record
Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
May 2025Sept 2027
28 mo
Signals from filings & records
No approved insolvency matchIBBI
No IBBI announcement has been matched to this builder after review.
IBBI public announcements
Projects
Proposed Red On Plot Bearing Fp No 40 Of Tps III Village Borivali West Mumbai
P51800052303 · Borivali