BUILDER

V M Constructions

Type Firm / individualRERA projects 2Districts Thane
BUILDER THOK
Pakka
1 of 1projects with possession moved
4 moaverage extension when late
0lapsed registrations
2MahaRERA projects · 1 being verified

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Dec 2027Apr 2028
4 mo
Mohan Palms
Navi Mumbai (M Corp.)
——
—

Signals from filings & records

Verification in progressMahaRERA

1 of 2 projects verified against the live MahaRERA record so far. Stats above use verified projects only.

Thok Bajaake crawler
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Mohan Samah
P51700053276 · Thane
Pakka
Mohan Palms
P51700011876 · Navi Mumbai (M Corp.)
Not scored