BUILDER

Vasundhara Builders

Type Firm / individualRERA projects 2Districts Mumbai Suburban
BUILDER THOK
Ruko
0 of 1projects with possession moved
0 moaverage extension when late
0lapsed registrations
2MahaRERA projects · 1 being verified

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Mar 2023Mar 2023
not moved
1 more project is being verified or has no declared dates yet.

Signals from filings & records

Verification in progressMahaRERA

1 of 2 projects verified against the live MahaRERA record so far. Stats above use verified projects only.

Thok Bajaake crawler
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Apna Desh CHS Ltd.
P51800017376 · Borivali
Ruko
Rbi Employees Siddhivinayak CHS LTD
P51800012461 · Borivali
Not scored