Dhyaan Do
3 of 4projects with possession moved
7 moaverage extension when late
1lapsed registrations
6MahaRERA projects · 2 being verified

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Kuber Antonia
Wakad · lapsed
Feb 2025Feb 2026
12 mo
Apr 2027Apr 2027
not moved
Apr 2027Aug 2027
4 mo
Aug 2027Dec 2027
4 mo
2 more projects are being verified or have no declared dates yet.

Signals from filings & records

Verification in progressMahaRERA

4 of 6 projects verified against the live MahaRERA record so far. Stats above use verified projects only.

Thok Bajaake crawler
1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Kuber Antonia
P52100035197 · Wakad
Ruko
Kuber Antonia C Wing
P52100053142 · Mulshi
Pakka
Kuber Antonia A Wing
P52100056209 · Mulshi
Pakka
Kuber Mudra Meadows
P52100077821 · Ambegaon
Pakka
Kuber Kunjban
P52100001616 · Pune (M Corp.)
Not scored
Kuber Imperia
P52100016321 · Wakad
Not scored