Vimal Gordhanbhai Pipalia

Type Firm / individualRERA projects 2Districts Pune
BUILDER THOK
Ruko
2 of 2projects with possession moved
81 moaverage extension when late
1lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Urja Cornerstone Building 1
Chakan (ct) · lapsed
Dec 2018Jun 2025
78 mo
Dec 2019Dec 2026
84 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Urja Cornerstone Building 1
P52100004993 · Chakan (ct)
Ruko
Urja Cornerstone Building 2
P52100006381 · Chakan (ct)
Ruko