BUILDER

Vinay Agrawal

Type Firm / individualRERA projects 4Districts Raigarh, Thane
BUILDER THOK
Ruko
3 of 4projects with possession moved
35 moaverage extension when late
0lapsed registrations
4MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Balaji Symphony
Shilottar Raichur
Dec 2018Dec 2018
not moved
Dec 2019Dec 2020
12 mo
Balaji Symphony Phase 3
Navi Mumbai (M Corp.)
Jun 2021Oct 2028
88 mo
Dec 2029Apr 2030
4 mo

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Balaji Symphony
P52000001043 · Shilottar Raichur
Ruko
Balaji Symphony Phase 2
P52000000754 · Akurli
Ruko
Balaji Symphony Phase 3
P51700000973 · Navi Mumbai (M Corp.)
Ruko
Balaji Symphony Phase 4
P52000029849 · Panvel
Pakka