BUILDER

Vinayaka Realtors And Developers

Type Firm / individualRERA projects 4Districts Mumbai Suburban
BUILDER THOK
Ruko
2 of 2projects with possession moved
26 moaverage extension when late
0lapsed registrations
4MahaRERA projects · 2 being verified

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Dec 2019Dec 2021
24 mo
Dec 2023Mar 2026
27 mo
2 more projects are being verified or have no declared dates yet.

Signals from filings & records

Verification in progressMahaRERA

2 of 4 projects verified against the live MahaRERA record so far. Stats above use verified projects only.

Thok Bajaake crawler
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Solomon Residency
P51800010650 · Kurla
Ruko
Rose Garden
P51800022587 · Andheri
Ruko
Nandadeep Residency
P51800015173 · Kurla
Not scored
Simra Residency
P51800029958 · Kurla
Not scored