BUILDER

Vtp Corpartion LLP

Type LLPRERA projects 2Districts Pune
BUILDER THOK
Ruko
2 of 2projects with possession moved
15 moaverage extension when late
1lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Jun 2021Dec 2022
18 mo
Purvanchal F Building
Kesnand · lapsed
Jun 2024Jun 2025
12 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Purvanchal Phase1 Ab
P52100001109 · Kesnand
Ruko
Purvanchal F Building
P52100021535 · Kesnand
Ruko