BUILDER

Waghere Promoters

Type Firm / individualRERA projects 3Districts Pune
BUILDER THOK
Dhyaan Do
2 of 3projects with possession moved
24 moaverage extension when late
1lapsed registrations
3MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Rajveer Creation
Pimpri Chinchawad (M Corp.) · lapsed
Dec 2022Jul 2026
43 mo
Dec 2025Dec 2025
not moved
Manikbaug Orchid
Pimpri Chinchawad (M Corp.)
Dec 2031Apr 2032
4 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Rajveer Creation
P52100018448 · Pimpri Chinchawad (M Corp.)
Ruko
Rajveer Nucleus
P52100009974 · Wakad
Dhyaan Do
Manikbaug Orchid
P52100010235 · Pimpri Chinchawad (M Corp.)
Pakka