BUILDER

Yashashree Developers

Type Firm / individualRERA projects 2Districts Ahmednagar, Pune
BUILDER THOK
Ruko
1 of 2projects with possession moved
24 moaverage extension when late
2lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Gulmohar Wing A
Pathardi(mc) · lapsed
Dec 2019Dec 2021
24 mo
Chandraprabha Residency
Haveli · lapsed
Dec 2023Dec 2023
lapsed

Signals from filings & records

2 projects lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Gulmohar Wing A
P52200014838 · Pathardi(mc)
Ruko
Chandraprabha Residency
P52100033482 · Haveli
Ruko