×Official RERA flags
RUKOUP RERA lists this project as: Default on QPR; NCLT proceedings.
Possession moved 26 months (Dec 2018 → Mar 2021); 67 months past the latest declared date; completion not confirmed in the register.
Mar 2021 is the latest possession date on UP RERA (checked 02 Nov 2026). The builder has not filed a newer extension, so the project is running past its own declared date.
Possession date passed? Work out the delay interest or refund RERA says the builder owes youDelay refund calculator →Open method: each factor's weight and what we found. Unchecked factors don't count for or against. How we score
No reviewed photos yet. Been to the site recently? Add one: it helps every buyer here.
Pre-booking checklist: what our records confirm, and what to ask the builder in writing.