Possession moved 29 months (Dec 2023 → May 2026); 5 months past the latest declared date; completion not confirmed in the register.
SCORE 13/100 · CONFIDENCE LOW
RERA possession
Dec 2023
Latest possession
May 2026
Units sold
Not disclosed
Status
Registered
Address
Construction of High Rise Residential Group Development along with incidental activities comprising 8 Blocks of Type-1A: Stilt Floor + 13 Floors with 156 dwelling units in each Block (1248 dwelling units), 1 Block of Type-1B: Stilt Floor + 13 Floors Residential building with 156 dwelling units, 7 Blocks of Type-2A: Stilt Floor + 13 Floors with 234 dwelling units in each Block (1638 dwelling units), 5 Blocks of Type–2B: Stilt Floor + 13 Floors Residential building with 234 dwelling units in each Block (1170 dwelling units), 2 Blocks of Type–3: Stilt Floor + 13 Floors Residential building with 195 dwelling units in each Block (390 dwelling units), 2 Blocks of Type–4A: Stilt Floor + 13 Floors Residential building with 247 dwelling units in each Block (494 dwelling units), 2 Blocks of Type–4B: Stilt Floor + 13 Floors Residential building with 247 dwelling units in each Block (494 dwelling un, Tamil Nadu
May 2026 is the latest possession date on TNRERA (checked 31 Oct 2026). The builder has not filed a newer extension, so the project is running past its own declared date.
Builder reported 98.5% physically complete to TNRERA for the quarter ending Sep 2023, against about 40% of the timeline elapsed. No newer progress report in 37 months.
Registered sale prices near this project, from the state's property registration records.
State registration records · coming soon
…Court cases
NOT CHECKED YET
RERA complaints, civil and consumer cases against the builder.
eCourts · e-Jagriti · coming soon
…Land title
NOT CHECKED YET
Land records and property card matched to the promoter.
State land records · coming soon
What the builder said, and what we found
POSSESSIONDOESN’T MATCH
Dec 2023RERA registration
May 2026Latest TNRERA date
Why this score
Open method: each factor's weight and what we found. Unchecked factors don't count for or against. How we score
Legal exposure 20%
—
Complaints and court cases not yet checked.
Title & approvals 10%
—
Land records and approvals not yet checked.
Delivery record 25%
0
Possession moved 29 months (Dec 2023 → May 2026); 5 months past the latest declared date; completion not confirmed in the register.
Promoter financial health 20%
—
Company filings not yet checked.
Disclosure accuracy 10%
—
Unit inventory not yet checked for this state.
Construction reality 15%
50
Builder reported 98.5% physically complete to TNRERA for the quarter ending Sep 2023, against about 40% of the timeline elapsed. No newer progress report in 37 months.
Recent photos
No reviewed photos yet. Been to the site recently? Add one: it helps every buyer here.
Before you pay a token
Pre-booking checklist: what our records confirm, and what to ask the builder in writing.
?
Project is registered with TNRERA and not lapsed ASK BUILDER
Registered · Dec 2021. TNRERA doesn't publish lapses: ask for the current registration or extension certificate.
×
Possession date has not been pushed back RUKO
Moved 29 months since registration. Get the current date written into your agreement.
✓
Builder is not in insolvency VERIFIED
No reviewed IBBI insolvency match. Company filings (MCA) are not yet checked.
?
Unit inventory is disclosed ASK BUILDER
Ask for the sold/unsold inventory as filed with TNRERA.
?
Clear land title ASK BUILDER
Ask for the title search report by an advocate and the latest land record (7/12 in Maharashtra, Jamabandi in Haryana, Khatauni in UP, Patta/Chitta in Tamil Nadu) showing the promoter as owner.
?
Commencement certificate (CC) and approved plans ASK BUILDER
Ask for the CC covering your floor and the sanctioned building plan.
?
Project bank account (70% escrow) ASK BUILDER
Pay only into the RERA designated account named in the registration. Ask for the account details in writing.
?
Carpet area as per RERA ASK BUILDER
The agreement must state carpet area (not super built-up) and match the RERA filing.
?
Payment linked to construction stages ASK BUILDER
No more than 10% before a registered agreement for sale; later instalments tied to construction milestones.
?
Lender approval ASK BUILDER
Ask which banks/HFCs have approved this project for home loans (APF). No approvals is a signal.