TNRERA TN/29/Building/0336/2023

L&T Realty Avinya Enclave

ठोक निर्णय
पक्का
85ठोक स्कोर

Builder reported 33% physically complete to TNRERA for the quarter ending Dec 2025, against about 46% of the timeline elapsed. No newer progress report in 10 months.

स्कोर 85/100 · विश्वास MEDIUM
RERA ताबा
Sept 2028
नवीनतम ताबा
Sept 2028
विकलेली युनिट्स
जाहीर नाही
स्थिती
Registered
पत्ता
Project Name: “L&T Realty Avinya Enclave” - Construction of 4 Residential cum Commercial Towers with Combined & Extended Triple Basement Floor; 3rd Basement Floor part (for Towers-3 & 4) + 2nd Floor & 1st Basement Floors (for Towers-2 to 5) over & above in Tower–2 & 3: Combined Ground Floor (for Towers-2 & 3) (2 dwelling units, Party Hall, Mini Theatre, Indoor Games, Multi-Purpose Hall, Squash Court, Spa and Swimming Pool Ground Level) + Combined 1st Floor (for Towers-2 & 3 (5 dwelling units, Gym & Yoga)) + 2nd Floor (Combined Tower–2 & 3 with 9 (5+4) dwelling units, Indoor Amenities) + 3rd Floor to 16th Floor in each Tower–2 & 3 with 10 dwelling units in each Floor, Totally 156 dwelling units in Tower-2 & 3; Tower–4: Ground Floor + 16 Floors with 397 dwelling units; Tower–5: Ground Floor + 16 Floors with 427 dwelling units Totally 980 dwelling units, abutting Mount–Poonamallee Road comp, Tamil Nadu
नकाशात उघडा ↗
पूर्ण ठोक रिपोर्ट₹149
  • एकाच दस्तऐवजात प्रत्येक निष्कर्ष, स्कोर कसा काढला आणि प्रत्येक अधिकृत स्रोत
  • टोकन देण्याआधी बिल्डरला विचारायचे नेमके प्रश्न
  • कुटुंब किंवा वकिलासोबत शेअर करण्यासाठी PDF
₹50 लाखांच्या घराच्या 0.05% पेक्षाही कमी.
रिपोर्टमधील एखादी माहिती चुकीची असल्यास कळवा, आम्ही पैसे परत करू.
TNRERA नोंदींमधील तपशील प्रकाशित स्वरूपात (इंग्रजीत) दिसतो.
!Construction progress (builder-reported)
ध्यान दो
Builder reported 33% physically complete to TNRERA for the quarter ending Dec 2025, against about 46% of the timeline elapsed. No newer progress report in 10 months. 498 units reported booked.
…किंमत
तपासणी बाकी
या प्रकल्पाजवळच्या नोंदणीकृत व्यवहारांच्या किमती, राज्याच्या मालमत्ता नोंदणी नोंदींमधून.
राज्य नोंदणी नोंदी · लवकरच
…न्यायालयीन खटले
तपासणी बाकी
बिल्डरविरुद्ध RERA तक्रारी, दिवाणी आणि ग्राहक खटले.
ई-कोर्ट · ई-जागृती · लवकरच
…जमिनीची मालकी
तपासणी बाकी
जमिनीच्या नोंदी आणि प्रॉपर्टी कार्ड प्रवर्तकाशी जुळवणे.
राज्य भूमी नोंदी · लवकरच

बिल्डरने काय सांगितले, आणि आम्हाला काय आढळले

POSSESSIONजुळते
Sep 2028RERA registration
Sep 2028Unchanged

हा स्कोर का

खुली पद्धत: प्रत्येक घटकाचे वजन आणि आम्हाला काय आढळले. ज्यांची तपासणी बाकी आहे ते बाजूने किंवा विरोधात मोजले जात नाहीत. आम्ही कसे तपासतो

कायदेशीर जोखीम 20%
—
Complaints and court cases not yet checked.
मालकी आणि परवानग्या 10%
—
Land records and approvals not yet checked.
वेळेवर ताबा 25%
100
On schedule for Sep 2028 so far.
बिल्डरची आर्थिक स्थिती 20%
75
No IBBI insolvency announcement against the promoter. MCA filings not yet checked.
माहितीची अचूकता 10%
—
Unit inventory not yet checked for this state.
बांधकामाची वस्तुस्थिती 15%
50
Builder reported 33% physically complete to TNRERA for the quarter ending Dec 2025, against about 46% of the timeline elapsed. No newer progress report in 10 months.

Recent photos

No reviewed photos yet. Been to the site recently? Add one: it helps every buyer here.

टोकन देण्याआधी

बुकिंगआधीची यादी: नोंदी काय पक्के करतात, आणि बिल्डरकडून लेखी काय मागायचे.

  1. ?
    प्रकल्प TNRERA मध्ये नोंदणीकृत आहे आणि लॅप्स झालेला नाही बिल्डरला विचारा
    नोंदणीकृत · ऑग २०२३. TNRERA लॅप्स प्रसिद्ध करत नाही: सध्याचे नोंदणी किंवा मुदतवाढ प्रमाणपत्र मागा.
  2. ✓
    ताबा तारीख पुढे ढकललेली नाही पक्का
    RERA ताबा तारीख करारात लिहून घ्या.
  3. ✓
    बिल्डर दिवाळखोरीत नाही पक्का
    तपासलेली कोणतीही IBBI दिवाळखोरी जुळणी नाही. कंपनी फायलिंग (MCA) ची तपासणी बाकी.
  4. ?
    युनिट्सची माहिती जाहीर केली आहे बिल्डरला विचारा
    TNRERA मध्ये भरलेली विकलेली/उरलेली युनिट्सची यादी मागा.
  5. ?
    जमिनीची स्पष्ट मालकी बिल्डरला विचारा
    वकिलाचा टायटल सर्च रिपोर्ट आणि प्रवर्तक मालक दाखवणारी जमिनीची ताजी नोंद (महाराष्ट्रात 7/12, हरियाणात जमाबंदी, यूपीमध्ये खतौनी, तमिळनाडूत पट्टा/चिट्टा) मागा.
  6. ?
    कमेन्समेंट सर्टिफिकेट (CC) आणि मंजूर नकाशा बिल्डरला विचारा
    तुमच्या मजल्यापर्यंतचे CC आणि मंजूर इमारत नकाशा मागा.
  7. ?
    प्रकल्प बँक खाते (70% एस्क्रो) बिल्डरला विचारा
    पैसे फक्त नोंदणीत नमूद RERA खात्यातच भरा. खात्याचा तपशील लेखी घ्या.
  8. ?
    RERA नुसार कार्पेट एरिया बिल्डरला विचारा
    करारात कार्पेट एरिया (सुपर बिल्ट-अप नव्हे) नमूद असावा आणि RERA फायलिंगशी जुळावा.
  9. ?
    बांधकामाच्या टप्प्यांशी जोडलेले पेमेंट बिल्डरला विचारा
    नोंदणीकृत करारापूर्वी 10% पेक्षा जास्त नाही; पुढचे हप्ते बांधकामाच्या टप्प्यांशी जोडलेले असावेत.
  10. ?
    बँकांची मंजुरी बिल्डरला विचारा
    कोणत्या बँका/HFC नी गृहकर्जासाठी हा प्रकल्प मंजूर केला ते विचारा. मंजुरी नसणे हा एक संकेत आहे.