BUILDER DELAY INDEX · SINDHUDURG
Which builders push possession back?
Every builder with at least 5 registered projects in Sindhudurg whose original possession date has already passed, ranked by how many months that date moved on the official RERA record.
By cityPuneThaneMumbai SuburbanRaigarhNashikPalgharNagpurMumbai CityAurangabadRatnagiriSataraSangliKolhapurSolapurAhmednagarAmravatiSindhudurgWardhaJalgaonChandrapur
292projects past their original possession date
34%had the date pushed back
12.2 moaverage delay per project
Most delayed
BuilderAvg delayPushed backProjects dueRuko
1Consortexe Properties PVT LTD9 mo20% of 555Least delayed
Builders with no lapsed registration and at most a quarter of projects at Ruko.
BuilderAvg delayPushed backProjects dueRuko
How it's measured: for each project, months between the possession date first declared to the regulator and the latest one (zero if unchanged), averaged per builder. Only records we have verified against the regulator count; cancelled and withdrawn registrations are excluded. A delay on the record is not by itself a finding of fault. See the methodology.