BUILDER DELAY INDEX · AURANGABAD
Which builders push possession back?
Every builder with at least 5 registered projects in Aurangabad whose original possession date has already passed, ranked by how many months that date moved on the official RERA record.
By cityPuneThaneMumbai SuburbanRaigarhNashikPalgharNagpurMumbai CityAurangabadRatnagiriSataraSangliKolhapurSolapurAhmednagarAmravatiSindhudurgWardhaJalgaonChandrapur
850projects past their original possession date
23%had the date pushed back
7 moaverage delay per project
Most delayed
BuilderAvg delayPushed backProjects dueRuko
1Tirupati Builders And Developers15 mo40% of 5552Sara Infrastructures9 mo20% of 5543Rahul Baswant Nandgawali6 mo40% of 5554Vikas Laxman Chaudhary5.3 mo25% of 8885Sara Properties4.8 mo40% of 5556Bhuvi Landmarks LLP1.5 mo13% of 8877Bhaishree Ventures1.2 mo20% of 555Least delayed
Builders with no lapsed registration and at most a quarter of projects at Ruko.
BuilderAvg delayPushed backProjects dueRuko
How it's measured: for each project, months between the possession date first declared to the regulator and the latest one (zero if unchanged), averaged per builder. Only records we have verified against the regulator count; cancelled and withdrawn registrations are excluded. A delay on the record is not by itself a finding of fault. See the methodology.