BUILDER DELAY INDEX · BELAGAVI

Which builders push possession back?

Every builder with at least 5 registered projects in Belagavi whose original possession date has already passed, ranked by how many months that date moved on the official RERA record.

355projects past their original possession date
31%had the date pushed back
2.9 moaverage delay per project

Most delayed

BuilderAvg delayPushed backProjects dueRuko
1Chaitanya Kulkarni1.8 mo20% of 551

Least delayed

Builders with no lapsed registration and at most a quarter of projects at Ruko.

BuilderAvg delayPushed backProjects dueRuko

How it's measured: for each project, months between the possession date first declared to the regulator and the latest one (zero if unchanged), averaged per builder. Only records we have verified against the regulator count; cancelled and withdrawn registrations are excluded. A delay on the record is not by itself a finding of fault. See the methodology.