BUILDER DELAY INDEX · MYSORE
Which builders push possession back?
Every builder with at least 5 registered projects in Mysore whose original possession date has already passed, ranked by how many months that date moved on the official RERA record.
By cityBengaluru UrbanMysoreDakshina KannadaBengaluru RuralBelagaviBallariKalaburagiDharwadUdupiChikkaballapuraShivamoggaKolarTumakuru
562projects past their original possession date
36%had the date pushed back
3.8 moaverage delay per project
Most delayed
BuilderAvg delayPushed backProjects dueRuko
1Mahendra Developers8.4 mo40% of 5552Saha Developers & Promoters7.6 mo77% of 262653Ess & Ess Infrastructure Private Limited7.2 mo78% of 6060164Yesh Developers & Promoters4 mo44% of 9905Sankalp Constructions Private Limited4 mo50% of 6606Sathyanarayana Y S1.8 mo20% of 553Least delayed
Builders with no lapsed registration and at most a quarter of projects at Ruko.
BuilderAvg delayPushed backProjects dueRuko
How it's measured: for each project, months between the possession date first declared to the regulator and the latest one (zero if unchanged), averaged per builder. Only records we have verified against the regulator count; cancelled and withdrawn registrations are excluded. A delay on the record is not by itself a finding of fault. See the methodology.