BUILDER DELAY INDEX · DAKSHINA KANNADA
Which builders push possession back?
Every builder with at least 5 registered projects in Dakshina Kannada whose original possession date has already passed, ranked by how many months that date moved on the official RERA record.
By cityBengaluru UrbanMysoreDakshina KannadaBengaluru RuralBelagaviBallariKalaburagiDharwadUdupiChikkaballapuraShivamoggaKolarTumakuru
435projects past their original possession date
43%had the date pushed back
5.4 moaverage delay per project
Most delayed
BuilderAvg delayPushed backProjects dueRuko
1Shalimar Realty Holdings14.4 mo80% of 5552S S Realty13.3 mo71% of 7753Matha Developers PVT LTD11.4 mo60% of 5534Northernsky Properties10.8 mo80% of 5515Vishwas Bawa Builders9.2 mo83% of 6656Lathish Suvarna6.6 mo60% of 5537Citadel Developers6 mo71% of 7708Marian Projects PVT. LTD.6 mo40% of 5519Land Trades Builders And Developers Private Limited5.1 mo50% of 1010110Poonam Builders4.3 mo29% of 77111Lotus Properties3.2 mo22% of 99412Ganesh M P3 mo29% of 772Least delayed
Builders with no lapsed registration and at most a quarter of projects at Ruko.
BuilderAvg delayPushed backProjects dueRuko
How it's measured: for each project, months between the possession date first declared to the regulator and the latest one (zero if unchanged), averaged per builder. Only records we have verified against the regulator count; cancelled and withdrawn registrations are excluded. A delay on the record is not by itself a finding of fault. See the methodology.